Last year, we installed solid oak hardwood floor in our main bedroom and family room. To our dismay, when we ripped up the old carpet, we found that the whole subfloor was covered with particle board. Using a standard nail gun to install the floor was out of the question–particle board isn’t structurally sound enough to “bite” nails.
Removing the particle board was impossible–it was completely glued down to the plywood. We ended up using screws instead of nails, making it bomb-proof at 3x the labor. Here’s a step-by-step how.
Hardwood floor nowadays is manufactured as tongue-and-groove and quickly installed with a nail gun and standard 1.75″ length nails.
Hardwood floor is 0.75″ thick. If you’re nailing at a 45-degree angle, this would be a total of ~1″ before you get to the plywood (0.75″ x sqrt(2)). Since the nails are 1.75″ long, that’s about 0.75″ of nail to dig into the plywood subfloor, which is great.
If you have both 0.75″ hardwood and 0.5″ particle board before you hit plywood, you have nothing left of the nail to dig into the plywood.
You’re pretty much left up shit’s creek with no good options. You could (a) replace the whole subfloor, (b) have a hard time finding a contractor to take your job, then pay them an exhorbitant amount–we were quoted $15k for labor alone, or (c) suck it up and drill each and every hole instead of using a nail gun.
With 2 people, it worked out really well to have one person as the layout-runner and one person as the driller. The layout-runner chooses boards for an entire row, tapping them into place, and cutting the last board to length.
Unfortunate person #2 gets to drill holes every 6-8″. We found we needed to drill pilot holes, or the screws would crack the tongue.
Starting a room is pretty easy–just put some door shims so you have ~0.25″ before the wall to allow for expansion. Ending is a bit more difficult.
You’ll have to use a table saw to cut the last row to width, then top drill. The last tongue is still intact, and required just a little bit of jiggering to set in place. Fill holes with Plastic Wood.
We found that we could handle only about 4hrs a day working on the floor–it’s a lot of being on your knees and drilling. The plus side of all that work is it’s bomb-proof. Good luck to the next person who wants to replace the floor!
There’s no squeaks whatsoever, and we don’t expect there to ever be. Whatever minor creaks were there initially are gone. We think any pressure on the floor actually helps screw them in tighter.
Program Management: the often reactively assigned role that's critical for business efficiency and scalability. The…
What you'll learn "How does your son eat so well?" is the number one question…
What you'll learn This article is part of the Camper Van Conversion series, focusing on…
What you'll learn This article is part of the Camper Van Conversion series and explains…
What you'll learn This article is part of the Camper Van Conversion series and details…
1. Creative Grids Rulers Their non-slip back actually works and their markings are clear and…